After approving your proposal we provide shop drawings and
field measure before fabrication starts.
General scheduling requirements
Before jobsite framing is complete:
1. Award project and send us the floor plan CAD file from the architect. Our goal is to send submittals within 2 weeks
2. Return approved submittals ASAP. Required one week prior to framing completion
3. Material is ordered. Material lead times start
After jobsite framing is complete:
4. Field measure
5. 6-8 weeks for fabrication
6. Install is scheduled